Hi We have a Corroded metal crib wall. We proposed at soldier pile wall to replace it. But due to overhead utility lines, that is not feasible. What are the other options? We prefer a top down construction. Thanks.
For a bridge foundation, we have 24" dia open end pipe piles. I wrote the foundation report (FR), and in FR, center relief drilling was recommended if hard driving is encountered. But the contractor (for construction) suggests installing 24-in diameter pipe piles using Pre-drilling to avoid...