The attached is a MPP file of the issue I am experiencing. For instance, if you change duration line time to 2hr there will be an 8hr start/finish interval instead it stating 2hr. Thanks for your help...
In the attached document is the example of what I am experiencing. Thanks
http://files.engineering.com/getfile.aspx?folder=71c90ef4-dc32-419e-8f0f-bb4c8e6e04d7&file=~MyBitmap.Bmp
Hello. The issue I am experiencing is that when I a one hour duration on a line (project) but the task displays a start/finish interval of 8 hours. No matter what duration I place in for my project for example, 2 hours - the task always displays a 8 hour gap. Can anyone help? Thanks