  1. sewerdesigner

    Earthwork, CUT FILL revisions

    Also.. In addition to what I said earlier, it is very important to state your assumptions. If you remove 6" of topsoil, state that in your final results. You are on the right track, just remember it is important that contractors can read and understand your results.
  2. sewerdesigner

    Earthwork, CUT FILL revisions

    If you are using Land Desktop, you can simply raise/lower your surface by a set amount. You'll get a fairly accurate number on large sites, but on small sites you have to be careful around the edges and determine if it impacts your calculations.
  3. sewerdesigner

    Maximum Slope 8" sanitary sewer

    Thanks Maury.... That is what I suspected but I wanted to get another opinion. I've heard about the water leaving the solids with pipes laid at a steep grade from several people over the last 12 years, but I've never heard another engineer express this concern. Has anybody had a problem with...
  4. sewerdesigner

    Maximum Slope 8" sanitary sewer

    We have a project that essentially places 20 homes on a hill side. The private roads accessing these homes will be roughly 10-11% We will be starting design of the gravity sewer system. The gravity sewer will be located close to the road, i.e. 10% grade at the surface. By code, we have to...