Thanks for all of your thoughts. There are still a lot of items we are taking into consideration, including setting up seismic monitoring equipment at the dam, any necessary traffic control (major road 150 meters away), alternative methods of demolition, environmental concerns (located near a...
I am involved in a project that is required to remove two dozen large sandstone boulders from a location that is about 100 meters downstream from a major dam. These boulders are approx. 10m x 5m x 3m in size. Would it be better to remove the rocks by breaking them into smaller sizes using...