Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Search results for query: *

  1. tocoadog

    ESAL Determination for WB-50 Classification

    I have a project for a temporary construction road based on 19 months of traffic consisting of WB-50 vehicles (semitrailer combination). How do I determine the ESALs for this temporary road to determine a pavement thickness? My recommendation to the client was a gravel road, however, they are...
  2. tocoadog

    Haul Road Design?

    I have a meeting next week to discuss the design of a haul road for a SpacePort construction here in New Mexico. The NMDOT hopes to use gravel/base course as the temporary haul road surface treatment. I already have a copy of the FHWA/South Dakota DOT "Gravel Roads - Maintenance and Design...
  3. tocoadog

    Asphalt Signs of Distress

    Everyone, I'm looking for a book that teaches the who, what, when and how of asphalt distress. For example, what causes bleeding? What causes alligator cracking? The cracking in this particular pavement section is considered bottom-up cracking because...sort of thing. Anyone have any ideas...
  4. tocoadog

    Triaxial Testing - Which test to run at which situation?

    CD, CU, Quick Test. I was asked by a junior engineer that this morning, and I couldn't answer with confidence. Any comments would be appreciative. I have very little experience with clays, but in the past we have always performed drained tests on sands. Also, shouldn't you always run...
  5. tocoadog

    Coefficient of Friction b/t clay and concrete base

    Anyone have a table or a reference? I have a sand reference but nothing on clay? Also, is this dependent on the adhesion like a pile? Thanks.
  6. tocoadog

    Deep Soil Mixing?

    Thanks for all the responses. And any sort of dynamic compacton is not feasible on this site. Short story: The owner of the property, a concrete manufacturer, decided against a reputable geotech company in the past. So, structures to the north and east of this particular site, structures...
  7. tocoadog

    Deep Soil Mixing?

    Have a site in NM for a large retail center. Historical research indicates that the site was once a quarry for concrete and we understand spoils were backfilled uncontrolled with little to no compactive effort. Preliminary borings encountered about 25 to 33 +/- feet of loose to medium dense...
  8. tocoadog

    Deep Soil Mixing?

    Have a site in NM for a large retail center. Historical research indicates that the site was once a quarry for concrete and we understand spoils were backfilled uncontrolled with little to no compactive effort. Preliminary borings encountered about 25 to 33 +/- feet of loose to medium dense...
  9. tocoadog

    Monolithic concrete pour with turned down edges?

    JAE, thanks for the quick response. Re: limiting the engineered fill thickness, I was thinking along the same lines as you in that the turned-down edges are rigidly connected to the slab thus able to distribute the load to a larger area...essentially a mat foundation. Larger area of load...
  10. tocoadog

    Monolithic concrete pour with turned down edges?

    BTW, I did a search on the site for the topic and found a post for the structural perspective but nothing for the geotechnical perspective. Looking forward to any of your replies.
  11. tocoadog

    Monolithic concrete pour with turned down edges?

    Contractor wants to build wharehouse with a monolithic pour with turned down edges. I understand this to be that the perimeter of the slab consists of turn down footings. Okay. For the geotech report, I based my allowable bearing pressure on spread foundations bearing on 48 inches of...
  12. tocoadog

    Rock anchor uplift capacity?

    Thanks for the quick response. In terms of bond area, should I just assume an area? I think this is what I'm having problems with. Should I provide the uplift capacity or just the bond strength of the grout and rock interface? And yeah, I agree, I need to buy the PTI book. Thanks again.
  13. tocoadog

    Allowable Soil pressure in New Mexico

    Another view to look at, if the rock is that shallow, a mat foundation may be more reasonable.
  14. tocoadog

    Rock anchor uplift capacity?

    Was wondering if someone had any insight on determining the uplift capacity on a rock anchor? Doing some tower work, with shallow refusal (<6 feet), structural engineer wants pier and mat foundation recs. Well, to prevent uplift in the mat, rock anchors have been recommended. The only thing...
  15. tocoadog

    Design of Friction Piles

    If you go with a driven foundations, you can download a freeware program called "driven" from FHWA. I don't have a link, but I have the program and use it regularly.
  16. tocoadog

    Allowable Soil pressure in New Mexico

    I work in Albuquerque, and unless you are in the extreme eastern part of the city, shallow rock shouldn't be encountered. We have the Sandia mountains that border the eastern part and I've had borings refuse at 3 feet in decomposed granite. As for the bearing values, those seem reasonable to...
  17. tocoadog

    Stiffness and Elastic Shortening re: Micropiles

    Everyone Long story short, City of Albuquerque, NM, US, is looking to add 2 lanes of bikepath between 2 opposing lanes of a 2 span bridge. Area is tight (less than about 20 feet) and utilities are very near. Pipe piles due to vibrations are out, imo. The structural has asked for micropile...
  18. tocoadog

    Drilled Pier Uplift Resistance?

    Thanks for responding. Thicknesses consist of 0-17 feet, SM-SC. 17-40 feet, CL. Actually I misspoke in my original post. The sign configuration is still being designed but height limits could reach 200 feet with sign dimensions of 20 X 20 feet. The structural engineer is the one who...
  19. tocoadog

    Drilled Pier Uplift Resistance?

    Hello everyone. I am looking for advice on how to determine uplift resistance for drilled pier design? The pier is for a sign approaching 75 feet high. Soils consist of medium dense to dense (N of 15 to 33 bpf) silty clayey sand underlain by stiff to very stiff lean clay (LL 49, PI32). The...
Back
Top