Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

12% increased for temporary works BS8002 cl. 4.4.4.2

Status
Not open for further replies.

Trop99

Geotechnical
Apr 9, 2014
4
in BS8002 cl. 4.4.4.2

"The allowable stresses given therein may be increased by 12 % for temporary works of short duration."

Does this clause refer to only steel sheet pile or related temporary works such as strutting, waler etc?
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor