RRaghunath
Electrical
- Aug 19, 2002
- 1,733
The IEC60840 allows the 132kV cable to be tested by applying rated voltage (Uo of 76kV) for 24hrs. This is as an alternative to applying 132kV Phase-Earth for 1hr.
I would like to know
* How common is the 24hr testing practiced.
* Is the test performed by connecting the cable to the grid, in somewhat similar to Transformer Soak test.
Thanks in anticipation.