24 hr- (2 shift) Resource Sheet

Status
Not open for further replies.

johnbeavis

Mechanical
Mar 27, 2003
2
0
0
NZ
On a 2 shift project (2 x 12 hr shifts per day) what are the numbers of resources do I need to input as the "max units"
I have the following numbers per shift:
7 fitters
17 pressure welders
6 welders
10 riggers
10 labourers

Are these the correct "max units" I use or do I need to double up for the second shift?