I am new here, I need a help and advice from you guys...
As a Purchaser I assigned to a project that needs some 3.2 certification.
No restriction if the materials from stockiest/trader or Mill/Manufacturer.
So we got some pipes from stock which is API 5L PSL2 in 3.1 certification. in order to comply to the client requirement we have to do the additional test.
My question is if the following testing below are enough or correct to do the upgradation of 3.2 certification.
*Tensile Test
*Hardness Test
*Charpy Test
*Chemical Composition
*HIC test
Furthermore, I would like to ask as well if MPI is included to perform for the pipe mentioned above..
Thanks in advance guys and keep safe
I am new here, I need a help and advice from you guys...
As a Purchaser I assigned to a project that needs some 3.2 certification.
No restriction if the materials from stockiest/trader or Mill/Manufacturer.
So we got some pipes from stock which is API 5L PSL2 in 3.1 certification. in order to comply to the client requirement we have to do the additional test.
My question is if the following testing below are enough or correct to do the upgradation of 3.2 certification.
*Tensile Test
*Hardness Test
*Charpy Test
*Chemical Composition
*HIC test
Furthermore, I would like to ask as well if MPI is included to perform for the pipe mentioned above..
Thanks in advance guys and keep safe