The architect wants a wall that has a recess at between two slab levels. The bottom meter high of the wall is a 300mm thick cavity brickwork wall, the middle meter high is a 220mm brickwork wall and the top meter is 300mm thick cavity wall again.
I am trying to figure out the best way to support the top, wider wall. Any suggestions would be appreciated.
There are also cases where a window opening, 1.1m wide and 1m high is within the 220mm brickwork wall which also needs support.
I am trying to figure out the best way to support the top, wider wall. Any suggestions would be appreciated.
There are also cases where a window opening, 1.1m wide and 1m high is within the 220mm brickwork wall which also needs support.