Rasheed Khan
Mechanical
- Aug 22, 2016
- 10
A contractor y is developing his WPS by the supporting of another X- contractor PQR. All parameters are established by the contractor Y in his WPS in accordance with other X-Contractor PQR and these parameters are almost similar to the X-contractor PQR requirements. Is it allowed to develop the WPS by any Contractor with supporting PQR of any existing contractor per ASME IX Or ASME B31.3?