Me again – want to get my colleagues take on the following. The other day, our safety officer indicated in a meeting with our roads contractor who is building a large rockfill embankment that he “needs” to build the embankment by building an edge berm first, then infilling inside the berm with the layer. The berm is supposed to be for “safety” so that equipment doesn’t fall over the edge (1.75H:1V slope). Has anyone in our group ever built an embankment this way? Has anyone ever seen an embankment built this way? Sometimes I shudder and it isn’t that Indonesia is too cold . . . .