cvg
Civil/Environmental
- Dec 16, 1999
- 6,868
plans call for abandoning concrete pipes within a levee embankment by grouting. Am specifying at least 75 psi unconfined compressive strength at 56 days. Others have proposed using a structural grout commonly used for grouting masonry with a 28 day strength of 2,500 psi. Any thoughts on what the minimum requirements should be for the grout?