Greetings,
I have a question pertaining to Section 11.5.4.3 of ACI 318-02. It states that when Vs exceeds 2 Vc, then maximum spacing limit shall be d/4. In case an engineer decides to put more shear steel than necessary, does ACI force section 11.5.4.3 into effect? Because the way Vs is defined, it is not the required shear steel but provided shear steel. It almost seems that the code is penalizing you for being conservative, or am I missing something?
I have a question pertaining to Section 11.5.4.3 of ACI 318-02. It states that when Vs exceeds 2 Vc, then maximum spacing limit shall be d/4. In case an engineer decides to put more shear steel than necessary, does ACI force section 11.5.4.3 into effect? Because the way Vs is defined, it is not the required shear steel but provided shear steel. It almost seems that the code is penalizing you for being conservative, or am I missing something?