Our job requires the installation of cast-in-place concrete columns (both 18" and 24" square) to be placed under existing floor beams in a building on several levels at several defined locations. the columns, after being poured, will require to be jacked to a specified 'pre-load' force. we have determined we will jack from the bottom of the columns and I would like some input on the type of jack to use and possible ideas on the bottom connection. Our first look at it entails installing a flat jack beneath the column baseplate, possibly with a load cell between the flat jack and the bottom of the baseplate to measure the load. The baseplate would be installed on anchor bolts, supported by the leveling nuts and shims, with a sufficient gap underneath to place the flat jack and load cell, and the columns would be installed up to the beam connection at the top. After the concrete cures sufficiently, we then plan to jack the columns upward to the 'pre-load' force. Any ideas on whether the use of flat jacks is the best option? what about ideas regarding the best way to measure the preload, and once the jacking operation is complete, being confident that the 'pre-load' force is maintained as designed? The engineer also indicates that due to 'creep' in the new concrete, the force may need to be re-checked 2-3 years down the line, then re-jacked if needed prior to finally grouting in the baseplate. Another idea thrown out had to due with the use of belleville washers under the baseplate to verify the pre-load, or possible load cells placed directly inside the anchor bolts. any ideas would be welcomed.