NLEng1
Structural
- Nov 4, 2016
- 2
Hi Everyone,
I have been requested by a contractor to provide a sub-structure design for a small design-build bridge replacement project in Atlantic Canada. The tender package included a geotechnical report which was tailored towards shallow foundations; however, the client has requested that bored concrete piles be used instead. The geotechnical report is fairly generic with borehole logs (13m deep), SPT values, and soil layer classification. The boreholes primarily indicate a sandy gravel mixture with few cobbles and boulders (ie, glacial till)without encountering bedrock. I am concerned that critical data and interpretation has been omitted such as: shaft friction, end bearing resistance, adhesion freezing forces (ad-freeze), etc. Not to mention recommendations from a qualified geotechnical engineer on minimum embedment length, number of piles, spacing, construction method (dry, casing, slurry, etc.), etc.
I am a civil/structural engineer with a good understanding of geotechnical, and I am able to deduce the much of the required information from the SPT-N values based on Meyerhof, soil descriptions, etc. But regardless, I feel that this information should come from a geotechnical report.
FYI, the Canadian Highway Bridge Design Code (6.7.3) re-iterates many of the same items which should be included in a geotechnical report.
Initially, the contractor agreed that they have had similar concerns from other consultants. However, my resistance to provide them a design based on the current report has resulted in them seeking out another consultant who will provide a design based on the current report.
I am very curious on what others would do in a similar situation?
Thanks!
I have been requested by a contractor to provide a sub-structure design for a small design-build bridge replacement project in Atlantic Canada. The tender package included a geotechnical report which was tailored towards shallow foundations; however, the client has requested that bored concrete piles be used instead. The geotechnical report is fairly generic with borehole logs (13m deep), SPT values, and soil layer classification. The boreholes primarily indicate a sandy gravel mixture with few cobbles and boulders (ie, glacial till)without encountering bedrock. I am concerned that critical data and interpretation has been omitted such as: shaft friction, end bearing resistance, adhesion freezing forces (ad-freeze), etc. Not to mention recommendations from a qualified geotechnical engineer on minimum embedment length, number of piles, spacing, construction method (dry, casing, slurry, etc.), etc.
I am a civil/structural engineer with a good understanding of geotechnical, and I am able to deduce the much of the required information from the SPT-N values based on Meyerhof, soil descriptions, etc. But regardless, I feel that this information should come from a geotechnical report.
FYI, the Canadian Highway Bridge Design Code (6.7.3) re-iterates many of the same items which should be included in a geotechnical report.
Initially, the contractor agreed that they have had similar concerns from other consultants. However, my resistance to provide them a design based on the current report has resulted in them seeking out another consultant who will provide a design based on the current report.
I am very curious on what others would do in a similar situation?
Thanks!