autokoz
Structural
- Nov 9, 2006
- 6
Looking for practice is setting elevation of adjacent foundation elements. For spread and/or continuous wall footing(s) I have used the rule of thumb of 2 horizontal to 1 vertical unless soils report says something like 1 to 1 would be acceptable. Have used the same general rules for adjacent pile caps, bottom of caissons. Are there any other opinions or systems that do not follow this general practice?