Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

AI designs an electric grid for Australia's NEM

GregLocock

Automotive
Apr 10, 2001
23,625
Designing a power generation system that delivers an average of 24 gigawatts (GW) while accommodating the intermittency of renewables and aligning with typical daily demand curves requires a strategic mix of energy sources. Below is a proposed energy mix, along with associated costs and considerations:


Proposed Energy Mix


  1. Onshore Wind (30%)
    • Capacity: Approximately 24 GW installed capacity.
    • Capacity Factor: 30%
    • Average Contribution: 7.2 GW
  2. Solar Photovoltaic (PV) (25%)
    • Capacity: Approximately 40 GW installed capacity.
    • Capacity Factor: 15%
    • Average Contribution: 6 GW
  3. Offshore Wind (10%)
    • Capacity: Approximately 8 GW installed capacity.
    • Capacity Factor: 45%
    • Average Contribution: 3.6 GW
  4. Natural Gas (20%)
    • Capacity: Approximately 6 GW installed capacity.
    • Capacity Factor: 80%
    • Average Contribution: 4.8 GW
  5. Battery Storage (15%)
    • Capacity: Approximately 10 GW with 4-hour storage duration.
    • Role: To manage peak demand and balance intermittent renewable output.

Cost Estimates


  • Onshore Wind:
    • Levelized Cost of Electricity (LCOE): $40–$59 per megawatt-hour (MWh)
    • Total Annual Generation: 63,072 GWh
    • Annual Cost: Approximately $2.52–$3.72 billion
  • Solar PV:
    • LCOE: $27–$56 per MWh
    • Total Annual Generation: 52,560 GWh
    • Annual Cost: Approximately $1.42–$2.94 billion
  • Offshore Wind:
    • LCOE: $60–$100 per MWh
    • Total Annual Generation: 31,536 GWh
    • Annual Cost: Approximately $1.89–$3.15 billion
  • Natural Gas:
    • LCOE: $45–$108 per MWh
    • Total Annual Generation: 42,048 GWh
    • Annual Cost: Approximately $1.89–$4.54 billion
  • Battery Storage:
    • Cost: $209–$278 per kilowatt-hour (kWh) of installed capacity
    • Total Installed Capacity: 40,000 MWh
    • Total Capital Cost: Approximately $8.36–$11.12 billion
    • Annualized Cost: Assuming a 10-year lifespan, approximately $0.84–$1.11 billion per year

Total Annual Costs


  • Onshore Wind: $2.52–$3.72 billion
  • Solar PV: $1.42–$2.94 billion
  • Offshore Wind: $1.89–$3.15 billion
  • Natural Gas: $1.89–$4.54 billion
  • Battery Storage: $0.84–$1.11 billion

Total: Approximately $8.56–$15.46 billion per year


Considerations


  • Intermittency Management: The combination of wind and solar, complemented by battery storage and natural gas, aims to provide a stable and reliable power supply that matches typical daily demand curves.
  • Capacity Factors: Capacity factors are based on typical values for Australia:
    • Onshore Wind: 30%
    • Solar PV: 15%
    • Offshore Wind: 45%
    • Natural Gas: 80%
  • Battery Storage: Assumed to have a 4-hour storage capacity, suitable for managing daily peak demand and short-term fluctuations in renewable output.
  • Cost Variability: LCOE ranges reflect variations in technology, location, financing, and operational factors.
  • Inflation and Technological Advancements: Future costs may decrease due to technological improvements and economies of scale.

This proposed energy mix and cost estimate provide a framework for developing a reliable and cost-effective power generation system that aligns with Australia's renewable energy potential and typical demand patterns.



It should be noted that the new transmission lines need add a further $16B+maintenance , call that $2B per year.

So $17B/year for 24 GW= 8c/KWh in direct energy costs, which is not far off what we pay now. Of course it's used LCOE which is pretty political rather than accurate.
 
Replies continue below

Recommended for you

Replacing some of the renewables and gas with reactors gives

If we replace some of the wind, solar, and battery storage with 1 GW nuclear reactors to provide baseload power, the overall cost structure would change significantly. Below is an analysis comparing the original plan (dominated by renewables) with a nuclear-based alternative.


Scenario 1: Renewables-Based Mix (Original Plan)​

  • Average Output: 24 GW
  • Components: Onshore Wind, Offshore Wind, Solar, Natural Gas, Batteries
  • Total Annual Cost: AUD 8.56 – 15.46 billion
  • Additional Transmission Cost: AUD 16 billion (one-time investment)

Scenario 2: Nuclear-Based Mix

Changes:

  • Replace 12 GW of renewable + storage with 12 x 1 GW nuclear reactors
  • Reduce onshore wind, offshore wind, solar, and battery capacity accordingly
  • Keep some gas capacity for peak demand
  • Require less new transmission investment

Key Assumptions for Nuclear:

  • Capacity Factor: ~90%
  • LCOE (Levelized Cost of Electricity): AUD 90–150 per MWh
  • Capital Cost: AUD 8–12 billion per reactor (for 1 GW each)
  • Construction Time: 10–15 years

New Cost Breakdown:

  • 12 GW Nuclear: AUD 96–144 billion(capital cost)
    • Annually (assuming 40-year lifespan, 5% financing cost): AUD 6.4–9.6 billion
  • Remaining Renewables (12 GW mix of wind, solar, gas): AUD 4–6 billion per year
  • Reduced Transmission Costs: Possibly AUD 5–8 billion instead of AUD 16 billion

1740874075977.png
 

Part and Inventory Search

Sponsor