Hello everybody,
At present, I am designing a facility where dead bodies are brought for washing and finally sent to the visiting room where the relatives will have last look at it.
As per Ahsrae, we need to maintain min.10 air change rate (100% fresh air) in this washing area,due to this, huge amount of conditioned air to be supplied and exhausted and eventually, the the chiller capacity is becoming almost double with this ACH as compared to the normal design (by considering load from building envelope and occupants).
By considering 10 ACH: Plant Capacity = 240 Tons
By considering load due to building envelope and occupants: Plant Capacity = 165 Tons.
Can anybody advice me of reducing plant load without compromising air change requirement.
Thanks and regards,
At present, I am designing a facility where dead bodies are brought for washing and finally sent to the visiting room where the relatives will have last look at it.
As per Ahsrae, we need to maintain min.10 air change rate (100% fresh air) in this washing area,due to this, huge amount of conditioned air to be supplied and exhausted and eventually, the the chiller capacity is becoming almost double with this ACH as compared to the normal design (by considering load from building envelope and occupants).
By considering 10 ACH: Plant Capacity = 240 Tons
By considering load due to building envelope and occupants: Plant Capacity = 165 Tons.
Can anybody advice me of reducing plant load without compromising air change requirement.
Thanks and regards,