In equation A-3-1, is there a "typical" or rule of thumb regarding the value of N, the number of stress range fluctuations, for an industrial crane runway and its connections?
I have no idea how many lifts/day the Owner may make with his 5 ton crane. I searched the threads and the Internet for some guidance and should have started here first. I'm looking for a range of use for a "light" industrial operation.
I have no idea how many lifts/day the Owner may make with his 5 ton crane. I searched the threads and the Internet for some guidance and should have started here first. I'm looking for a range of use for a "light" industrial operation.