Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations waross on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Ammonia Tuning for Injections Rates to the Ammonia Injection Grid

Status
Not open for further replies.

HotPotato

Chemical
Apr 25, 2016
18
US
All,

I am working on a competitive bid for a potential customer which includes a replacement-in-kind of an Aq. NH3 vaporizer skid that has met its end of life. The item below was stated in their RFP:

The final installation shall include DCS loop check with site technicians and Ammonia
Tuning for injections rates to the Ammonia Injection Grid.

Could anybody please provide their opinion on what "Ammonia Tuning for injection rates to the Ammonia Injection Grid" means? We are certainly not expected to complete traverse testing and SCR tuning, so I am confused because all/any DCS work is excluded from the scope. Here are some other details:
[ul]
[li]No PLC on the new skid[/li]
[li]No VFDs on the skid (no characterizer curves to change for VFDs)[/li]
[li]No additional signals being run to the DCS (Replacing exactly in kind)[/li]
[/ul]

My only thought that I am hoping the community can deny/confirm is that the automated aq. NH3 globe control valve can have some field adjustments made to it?
 
Replies continue below

Recommended for you

Bad location for this question.

It appears that this ammonia injection grid is part of an environmental pollutant control system, ( but you are not telling us !!)

Post this in the "Chemical Environmental Control" Forum ....

MJCronin
Sr. Process Engineer
 
Why don't you issue a bid clarification request and post this query? That way you are going to get 100% complete answer.

Dejan IVANOVIC
Process Engineer, MSChE
 
I apologize if this is not the right sub-forum. I had searched for SCR discussions and found recent discussions regarding SCR systems here.
 
EmmanuelTop said:
Why don't you issue a bid clarification request and post this query? That way you are going to get 100% complete answer.

Good question! Since clarifications are handed out to all bidders, I always do as much research to find an answer before asking a clarifying question. Unnecessarily asking a clarifying question may aid a competitor. If I can't find an answer in a day or so, I would then reach out to the bidder.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top