Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

API 510 Section 7

Status
Not open for further replies.

Grammatico

Mechanical
Jul 30, 2007
11
Helo,

I have to rerating a pressure vessel which was alterated by welding in one of its nozzle. API 510 section 7 show the details to doing the reparation and rerating. Can I do the rerating if the welding was done without following the instructions of this section?
In 7.2.7 (Design) mention a temporary repair, can I consider my welding like that?
If I’ll do a metallographic, ultrasonic and visual inspection on my welding by an authorized pressure vessel inspector, can I consider that API 510 will accept my rerating?

Tank you, grammatico
 
Replies continue below

Recommended for you

the vessel was designed by ASME VIII Div.1 1998 to 2000
 
Rerating involves calculations per 7.3 a. Was the nozzle addition made without calculations and as a result do you need added reinforcement? If so, simply add the reinforcement required.

 
The alteration is not a reinforcement, in fact, the nozzle doesn’t need a reinforcement. I am talking about a replace of the original welding. The problem is that the new weld procedure isn’t exist.
 
So why are you rerating? If you welded in the new nozzle without a qualified welding procedure, write a Nonconformance Report defining such and stating that you will qualify the required procedure as the corrective action, obtaining concurrence of the Owner's Inspector. Once the procedure has been qualified, sign off on the Nonconfomance again obtaining concurrence of the Inspector.

 
Yes, but I am looking for another alternative, my intention is obtain the acceptation for API 510 of this welding.
 
API 510 doesn't accept anything. The owners Inspector does.

 
In API 510 7.2.10.- said: “Substituting nondestructive examination procedures for a pressure test after an alteration may be done only after a pressure vessel engineer experienced in pressure vessel design and the authorized pressure vessel inspector have been consulted.” How can I contact an authorized pressure vessel inspector?
 
The Inspector is the Owner's Inspector in possesion of an API 510 Certificate. Refer to 4.2.

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor