metboss
Petroleum
- Sep 12, 2012
- 152
Hi All,
As per our specification the required material grade is API 5CT T-95 PSL2
But, vendor will only be able to supply T-95 PSL1 instead of T-95-PSL2. What are the main differences between PSL-1 & PSL-2? Can we accept T-95 PSL1 ?
Regards
As per our specification the required material grade is API 5CT T-95 PSL2
But, vendor will only be able to supply T-95 PSL1 instead of T-95-PSL2. What are the main differences between PSL-1 & PSL-2? Can we accept T-95 PSL1 ?
Regards