pkhenry
Mechanical
- Jan 6, 2000
- 9
I am looking at purchasing a 1600'TDH 350 USGPM flow pump. The quotes cover horizontal split, at a much higher initial capital cost and horizontal stacked pumps. I understand the stacked units are higher in maintenance down time which may off set the initial capital. Are there any other issues I should be aware off. Basically the units are coming in the same regarding trim, # of stages and material. It seems only an issue of casing style.