Hi,
Daft and simple question.
I'm just raising a new PMA and I'm referencing ASME B31.3 as one of the standards applied.
ASME B31.3:2012 was issued in January 12th 2013 but has an effective date of six months after issue, July 2013.
Common practice, but I hadn't noticed it before.
Am I correct to reference a standard that isn't effective yet, or should I still reference ASME B31.3:2010.


Thanks.

Paul J
 
Replies continue below

Recommended for you

I'd reference the 2010 version, if the design contract will be signed before July.

Independent events are seldomly independent.
 
I've seen it both ways. Typically, as the engineer, I just but B31.1. Div 1 usually states something to the effect of " the latest version at time of contract signature." Be warry though. On a nuclear project, I had B31.1 or section VIII change from 50% margin to 20% (over 10 yrs ago). A contractor who had an older contract requiring 50% brought it to our attention. All contracts after that had an addendum stating the 50% margin as a requirement.
 