We are getting ready to install some o-lets on a piping run per customers drawing. One of the o-lets is located in the center of a circumferential butt-weld. The butt weld has been 100% radiographed prior to the o-let installation. A co-worked asked if this was allowed by B31.3? I've looked through the book multiple times and cant find anything that discussed it.
I've told the specific PM to contact Customer Inspector for clarification. Even doing so, I would still like to know where to find clarification in the book to make sure we are ok. I don't think its a good idea if everyone built stuff per customers recommendations, I am a firm believer in Manufactures responsibility as well. I want to agree/disagree with their clarification based on the code. Thanks in advance!
I've told the specific PM to contact Customer Inspector for clarification. Even doing so, I would still like to know where to find clarification in the book to make sure we are ok. I don't think its a good idea if everyone built stuff per customers recommendations, I am a firm believer in Manufactures responsibility as well. I want to agree/disagree with their clarification based on the code. Thanks in advance!