ore12
Mechanical
- Aug 6, 2015
- 2
We normally design gas processing skids under PED. However for this American project we have to work under ASME B31.3 and I want to verify a few things.
-This system falls under normal fluid service.
-We will source U-stamped pressure vessels and integrate those into the skids as our skid fabricator does not have a CoA.
-Max pressure: 290 psig, AISI 304, 300# flanges, max pipe size is 6".
1.) Is a NoBO required for design validation (assembly integration validation), PID validation?
2.) Is a flexibility calculation required? To my understanding this is not needed if T is below 150 °F.
3.) To my understanding the Client has to send an inspector to inspect the piping, correct?
4.) 100% VT and 5% RT of welds required.
5.) Are there any other requirements we need to be aware of when commissioning the skid on site?
Thanks!
-This system falls under normal fluid service.
-We will source U-stamped pressure vessels and integrate those into the skids as our skid fabricator does not have a CoA.
-Max pressure: 290 psig, AISI 304, 300# flanges, max pipe size is 6".
1.) Is a NoBO required for design validation (assembly integration validation), PID validation?
2.) Is a flexibility calculation required? To my understanding this is not needed if T is below 150 °F.
3.) To my understanding the Client has to send an inspector to inspect the piping, correct?
4.) 100% VT and 5% RT of welds required.
5.) Are there any other requirements we need to be aware of when commissioning the skid on site?
Thanks!