Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations MintJulep on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME B31.3 vents and drains in fuel gas system

Status
Not open for further replies.

qualitypro

Mechanical
Sep 30, 2003
91
Is NDE (RT) required on the welds in vent and drain lines after the last shutoff valve in a fuel gas system per B31.3?
Thanks
 
Replies continue below

Recommended for you

You do not tell us the size or the operating conditions.
I general if it is a Hydrogen & it is Butt Welded, and it is a ASME B31.3 Code plant then you RT is required.

prognosis: Lead or Lag
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor