wlcmech
Mechanical
- Feb 17, 2004
- 2
I have a flange that has 4 presuure taps drilled from the OD of the flange through to the ID. Does anyone know a reference showing how to verify this arrangement and its application in a ASME Section VIII Div1 pressure vessel design? I am more concerned how to account for the loss of material in the flange calculation. This is no longer a standard Appendix 2 flange calculation.