ASME I Capacity Change

Status
Not open for further replies.

loilfan

Mechanical
Jan 20, 2015
122
I've been told that the PSV capacity calculations from Section I changed at some point from 10*(Heating Surface Area) to (Boiler output in Btu/hr)/1000 as it's now written in PG-67.2.1.4.

Does anyone know at about what edition that change occurred?
 
Replies continue below

Recommended for you

Never mind, people. From my research into the old Codes, it seems that my colleague was thinking of ASME IV Table HG-400.1.
 