Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

ASME IX SUPPLEMENTARY ESSENTIAL VARIABLES 1

Status
Not open for further replies.

MALJUD2030

Petroleum
Jul 3, 2010
7
As per ASME IX QG-105.2, Supplementary essential variables become additional essential variables in situations where procedure qualifications require toughness testing. QW-251.2 states that Supplementary essential variables are required for metals for which other Sections specify notch‐toughness tests and are in addition to the essential variables for each welding process.

My query is whether supplementary essential variables are applicable if a client specifies the requirement of Impact Tests though it's not a requirement as per ASME B31.3.
 
Replies continue below

Recommended for you

My query is whether supplementary essential variables are applicable if a client specifies the requirement of Impact Tests though it's not a requirement as per ASME B31.3.

Yes, if the engineering contract or specification agreed upon requires impact testing. An owner/user can always request additional requirements above and beyond code minimum requirements as long as they are willing to pay for it.
 
He who holds the gold gets to make the rules.

Best regards - Al
 
Thanks Guys. ASME IX Introdiuction page states that "The toughness supplementary essential variables do not apply unless referenced by the Construction Codes". The Introduction does not indicate any reference to Client Specifications. I am a bit reluctant to apply the Impact Testing clause from the specification as the thickness range for the WPS per ASME B31.3 will become T to T+6mm where T is the qualification wall thickness.
 
If you elect not to comply with the contract you should not accept the job. You may find the customer may elect to declare the work completed as noncompliant and reject it. They may also elect to pursue civil action and seek damages for delays in their schedule. Funny how that works. The ramifications can be very painful financially and ruinous to the contractor's reputation in the business world. The Chinese manufactures are discovering the pitfalls of their well earned reputation of being under performers.

Best regards - Al
 
MALJUD2030;
Please read further in Section IX below;

(a) This Section contains requirements for the qualification
of welders, welding operators, brazers, brazing operators,
plastic fusing machine operators, and the material
joining processes they use during welding, brazing, and
fusing operations for the construction of components under
the rules of the ASME Boiler and Pressure Vessel Code,
the ASME B31 Codes for Pressure Piping, and other Codes,
standards, and specifications that reference this Section.
This Section is divided into four parts.
(1) Part QG contains general requirements for all
material-joining processes.
(2) Part QW contains requirements for welding.
(3) Part QB contains requirements for brazing.
(4) Part QF contains requirements for plastic fusing.
(b) Whenever the referencing Code, standard, or specification
imposes requirements different than those given
in this Section, the requirements of the referencing Code,
standard, or specification shall take precedence over the
requirements of this Section.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor