hwangbojin
Mechanical
- Mar 20, 2004
- 5
Dear Experts and help me;
Generally,we have been requested to design and test the fuel natural gas pressure conditioning facilities in accordance with ASME VIII div 1.
Specifically,we have been requested to design and constructe the natural fuel gas knock drum and filter for separation of condensate and mechnical material (working pressure:60 bars, working temp 60 oC) but we have not been requested to design and construct natural fuel gas waterbath heater and strainer and condensate tank (W.P:60 bar,W.T:60 oC).
Now,we have already designed and fabricated on the shop holding ASME "U" stamp the natural fuel gas nock drum,filter and waterbath eater, strainer, condesate tank in accordance with ASME VIII Div. 1 without AI's ceterfication and involvement. And then, the client is requesting "U" stamp in accordance with ASME VIII div 1. And we are explaining to the client that "U" stamp is not requested from the client only requested design and fabrication in accordance with ASME VIII Div 1. But the client is interpretating that the design and construction and test in accordance with ASME VIII Div.1 meanns essentially the vessels with "U" stamped vessel.
Eventually our prefabricated vessels for fuel gas system rejected by client and our further work is still stopped.
Therefore we questionnaire the following 4 question.
Please advise it urgently so that we can proceed next step.
QUESTION 1 : is it correct client's interpretation (the vessel in accordance with ASME VII Div. 1 means of vessel
with "U" stamp essentially)?
QUESTION 2 : We understand that the boiler in accordance with ASME I have been interpretated the boiler(vessel) with "S" and/or "A" essentially. How about the vessel in accordance with ASME VIII Div 1?
QUESTION 3 : What is our best way to minimize our big impact to apply "U" stamp on prefabricated fuel gas vessel?
QUESTION 4 : Is there any special procedure to apply ASME VIII Div. 1 "U" stamp on prefabricated pressure vessel for natural fuel gas vessel?
QUESTION 5 : Is it not helpful to obtain "U" stamp from AI if fabrication of vessel is carried out on shop holding "U" stamp holding ?
Best Regards,
hwangbo-jin
Generally,we have been requested to design and test the fuel natural gas pressure conditioning facilities in accordance with ASME VIII div 1.
Specifically,we have been requested to design and constructe the natural fuel gas knock drum and filter for separation of condensate and mechnical material (working pressure:60 bars, working temp 60 oC) but we have not been requested to design and construct natural fuel gas waterbath heater and strainer and condensate tank (W.P:60 bar,W.T:60 oC).
Now,we have already designed and fabricated on the shop holding ASME "U" stamp the natural fuel gas nock drum,filter and waterbath eater, strainer, condesate tank in accordance with ASME VIII Div. 1 without AI's ceterfication and involvement. And then, the client is requesting "U" stamp in accordance with ASME VIII div 1. And we are explaining to the client that "U" stamp is not requested from the client only requested design and fabrication in accordance with ASME VIII Div 1. But the client is interpretating that the design and construction and test in accordance with ASME VIII Div.1 meanns essentially the vessels with "U" stamped vessel.
Eventually our prefabricated vessels for fuel gas system rejected by client and our further work is still stopped.
Therefore we questionnaire the following 4 question.
Please advise it urgently so that we can proceed next step.
QUESTION 1 : is it correct client's interpretation (the vessel in accordance with ASME VII Div. 1 means of vessel
with "U" stamp essentially)?
QUESTION 2 : We understand that the boiler in accordance with ASME I have been interpretated the boiler(vessel) with "S" and/or "A" essentially. How about the vessel in accordance with ASME VIII Div 1?
QUESTION 3 : What is our best way to minimize our big impact to apply "U" stamp on prefabricated fuel gas vessel?
QUESTION 4 : Is there any special procedure to apply ASME VIII Div. 1 "U" stamp on prefabricated pressure vessel for natural fuel gas vessel?
QUESTION 5 : Is it not helpful to obtain "U" stamp from AI if fabrication of vessel is carried out on shop holding "U" stamp holding ?
Best Regards,
hwangbo-jin