Hello all,
I have a question which may fall into an AI or Jurisdictional opinion, just checking if any of you have ever run into this.
For a multiple boiler installation with an economizer the diagram for drum style boilers shows the code stopping after the second valve from the boiler. This diagram is assuming the feedwater control station is before the economizer but in this case it is in between the economizer and boiler. With this configuration am I required to consider the feedwater piping to be code going from the second valve off the boiler to the economizer?
I have a question which may fall into an AI or Jurisdictional opinion, just checking if any of you have ever run into this.
For a multiple boiler installation with an economizer the diagram for drum style boilers shows the code stopping after the second valve from the boiler. This diagram is assuming the feedwater control station is before the economizer but in this case it is in between the economizer and boiler. With this configuration am I required to consider the feedwater piping to be code going from the second valve off the boiler to the economizer?