lostsailor
Structural
Gentlemen,
I am also posting this question on the Nuclear Engineering forums but since this one seems to get more traffic I hope
you will excuse my presumption.
A pressure vessel is to be constructed in accordance with ASME III-D requirements and will be constructed of P-4X material, radiographed in accordance with Code requirements, and subjected to a PWHT of 725 degrees F (the purpose of which has not yet been ascertained ).
As the PWHT is neither required nor prohibited by the Code, per Table ND-4622.1-1, it has been suggested that the vessel can be subjected to RT prior to the PWHT being done with no additional NDE after PWHT, as stipulated in ND-5120.
My read on this is regardless of whether or not PWHT is mandated by the Code, RT should always be performed after PWHT, unless specifically exempted by the Code, due to the possible complications arising from the PWHT process.
Just looking for some additional opinions.
Regards,
RLS
I am also posting this question on the Nuclear Engineering forums but since this one seems to get more traffic I hope
you will excuse my presumption.
A pressure vessel is to be constructed in accordance with ASME III-D requirements and will be constructed of P-4X material, radiographed in accordance with Code requirements, and subjected to a PWHT of 725 degrees F (the purpose of which has not yet been ascertained ).
As the PWHT is neither required nor prohibited by the Code, per Table ND-4622.1-1, it has been suggested that the vessel can be subjected to RT prior to the PWHT being done with no additional NDE after PWHT, as stipulated in ND-5120.
My read on this is regardless of whether or not PWHT is mandated by the Code, RT should always be performed after PWHT, unless specifically exempted by the Code, due to the possible complications arising from the PWHT process.
Just looking for some additional opinions.
Regards,
RLS