Hi friends,
My question is regarding ASME VIII Div. 1.
On a vessel you have a stub for a field weld to a vapor duct. MY question is where does ASME code stop? Is it the end of the neck or is the field weld included? In the introduction of section 8 it states the first circumferential weld. Well does ASME cover the weld or not?

Thanks for your thoughts
 
Replies continue below

Recommended for you

....the welding end connection for the first circumferential
joint for welded connections [see
UW-13(h)];

The weld prep is under Section VIII, Div 1. The weld itself would be under a piping code or standard.
 
Thanks metengr for the reply
but 1 more quick question say you have a weld fit-up band for this weld instead of a butt-weld how would that be addressed because you are technically welding roughly 2 inches before the end of the nozzle neck?
 
the same theory apply to any any weld type.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor