FoxRox
Mechanical
- Feb 12, 2015
- 349
I'm using COMPRESS for calculations and getting the following deficiency:
I understand what this means (A3 from Figure UG-37.1 is non-existent), but I'm unable to find why this should be a deficiency, because the internal projection and internal weld are not required at all. The joint is per Figure UW-16.1(d) with added internal projection and an internal fillet weld. It is a UG-36(c)(3) exempt opening. It works out fine with no internal projection. Why should adding more material be a deficiency? UW-16(c) does not prohibit internal projections or internal welds. In fact, it permits them to be used and considered as extra reinforcement as necessary. But I'm not trying to claim reinforcement. I'm just trying to ease fabrication by not requiring the extra steps for the flush internal mount. Is there a section or paragraph I'm missing, or is this perhaps an oversight in the COMPRESS programming? I have submitted an inquiry but won't hear back before Monday. I curious if anyone here has insights. Thanks!
COMPRESS said:The area available in the nozzle internal projection (A3) is not contributing to the reinforcement as the nozzle
corrosion plus the vessel corrosion is larger than the nozzle thickness.
I understand what this means (A3 from Figure UG-37.1 is non-existent), but I'm unable to find why this should be a deficiency, because the internal projection and internal weld are not required at all. The joint is per Figure UW-16.1(d) with added internal projection and an internal fillet weld. It is a UG-36(c)(3) exempt opening. It works out fine with no internal projection. Why should adding more material be a deficiency? UW-16(c) does not prohibit internal projections or internal welds. In fact, it permits them to be used and considered as extra reinforcement as necessary. But I'm not trying to claim reinforcement. I'm just trying to ease fabrication by not requiring the extra steps for the flush internal mount. Is there a section or paragraph I'm missing, or is this perhaps an oversight in the COMPRESS programming? I have submitted an inquiry but won't hear back before Monday. I curious if anyone here has insights. Thanks!