cpands
Mechanical
- May 27, 2004
- 2
Under A/SA106-B pipe Markings are to include hydro test pressure. We are required to provide a certified MTR.
Do you conside the material to meet ASME requirements if the pipe shows a test pressure of 1780PSI and the MTR shows the correct test pressure of 1800PSI?
Do you conside the material to meet ASME requirements if the pipe shows a test pressure of 1780PSI and the MTR shows the correct test pressure of 1800PSI?