ASTM G48 method A suggests that 72hrs is a reasonable test period. All the specs that we have previously worked to have a test period of only 24hrs (Norsok, Shell, ExxonMobil etc)
Does anyone know of a spec that insists on a 72hr test period? We have a client who has an ongoing internal debate on whether to change their data sheets.
Does anyone know of a spec that insists on a 72hr test period? We have a client who has an ongoing internal debate on whether to change their data sheets.