FlowNBE
Mechanical
- May 3, 2007
- 8
I'm designing a vessel to meet B31.3-2004 requirements. I have a piece of rolled plate welded to a piece of round bar; both 304 SS. The plate is .3125 thick and the wall of the round bar after boring will be about 1.74" thick. B31.1 references B16.25 (Fig. 1 page 2) for butt weld transitions which shows a 2T long (no minimum designation) transition zone on the inside and outside. So, my transition zone on the outside should be about .625" long with the 30 and 45 and 90 degree angles. Seems short.
Looking at B31.1-2004, Fig. 127.4.2 page 72 shows a minimum transition zone of 2T. This seems to be opposite of B16.25-2003
Is it better to have a longer transition zone? Is there a conflict between these two standards?
Looking at B31.1-2004, Fig. 127.4.2 page 72 shows a minimum transition zone of 2T. This seems to be opposite of B16.25-2003
Is it better to have a longer transition zone? Is there a conflict between these two standards?