vipineng
Electrical
- Jan 5, 2016
- 12
Hello,
I have an issue with my transformer charging.Transformer ratings are 110 MVA,132/11 kV Three phase.This transformer has to be commissioned in a short period .But the problem is there is no 132 kV supply line from the switchyard which is in under construction.My question is ,can we charge the transformer by 11kV?....Please provide valuable suggestions.
.I heard about back charging concept.But i don't know the process.
I have an issue with my transformer charging.Transformer ratings are 110 MVA,132/11 kV Three phase.This transformer has to be commissioned in a short period .But the problem is there is no 132 kV supply line from the switchyard which is in under construction.My question is ,can we charge the transformer by 11kV?....Please provide valuable suggestions.
.I heard about back charging concept.But i don't know the process.