Can we enegize a 240MVA 275/132kV step up transformer under no load condition by using the 132kV source due to 275kV incoming line is not ready.
The 240MVA transformer will put under "soak" condition.
BTW, can we use a step up transformer as a step down transformer?
Thanks.