maxPE
Nuclear
- Feb 1, 2003
- 21
As an ME Im a little out of my field but I have a 3000 foot overhead run to make from where Edison wants to put the meter in (4 wire/277/480) to my well. I was thinking of using a std residential type xformer to step up the 277/480 to 4800 or another voltage for the run and then step it down at the terminus for the well pump (240vac, 30 hp). Is this a 'bad' idea? Reversing the xformer feed direction incures losses or danger or? Does anyone have a better idea or is this reasonable. I was hoping to use surplus or used xformers. BTY, this is on my own farm. Thanks!
Max Hovaten P.E.
Max Hovaten P.E.