s0hxy
Mechanical
- Mar 13, 2008
- 14
I am having a problem with the following:
Engineering
Task 1
Procurement
Task 2
Task 1 will start after Task 2 is complete. I would like to create a sort of backward FS (Task2>Task1). Question: Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship. Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.
Any help with this would be greatly appreciated.
Regards
Engineering
Task 1
Procurement
Task 2
Task 1 will start after Task 2 is complete. I would like to create a sort of backward FS (Task2>Task1). Question: Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship. Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.
Any help with this would be greatly appreciated.
Regards