Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Backward Schedule (Is it possible?)

Status
Not open for further replies.

s0hxy

Mechanical
Mar 13, 2008
14
I am having a problem with the following:

Engineering
Task 1
Procurement
Task 2


Task 1 will start after Task 2 is complete. I would like to create a sort of backward FS (Task2>Task1). Question: Is this possible w/o moving Task 1 below Task 2 and creating a FS relationship. Moving Task 1 below Task 2 would create a problem with the layout (presentation) of the schedule.

Any help with this would be greatly appreciated.

Regards
 
Replies continue below

Recommended for you

Why didn't you just try it?

MSP doesn't care what order the tasks are laid out relative to the predecessor/successor relationship.

TTFN

FAQ731-376
 
Thanks.

I have tried this in the past and was unsuccessful.

To be more specific:

1.0 Engineering
Complete As built Drawings (15days) “start date to be determined by relationship”

2.0 Commissioning
Commission Plant #1 (10 days) Mar 01 to Mar 05
Commission Plant #2 (10 days) Mar 20 to Mar 30
Commission Plant #3 (10 days) June 30 to July 20

I would like to present the above as is on the schedule. I do not want to put the Engineering summary underneath the Commissioning summary.

As it stands now, as built drawings can only start after the last commissioning task (i.e. in this case Commission Plant #3) which would begin on July 21 and take 10 days to complete.

When I try to complete a FS relationship between C. Plant #3 and C. As built drawings the relationship shows the link arrow from Complete As built drawings to Complete Plant #3 rather than the other way around.

If this relationship is possible: Is it possible to link all commissioning activities to the Complete As built drawings so by default the Complete As built drawings would start after the finish of the last commissioning activity. This would be important during the project if Plant #1 became the last commissioning activity as opposed to Plant #3 OR is this something that the planner has to manually adjust if the sequence of activity changes
 
The relationship is possible. You're doing something wrong.

If last commision is line 10 and drawing is line 4, then line 4 should have 10FS in predecessor. Works every time.

TTFN

FAQ731-376
 
Thank you very much for help. It worked great but I had to manually type the 10FS relationship in the predecessor text box. Is there a way to use the FS button to establish this relationship?

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor