MPHenry
Structural
- Mar 16, 1999
- 53
I am currently designing a 3 storey reinforced concrete structure over basement on a very loose sand/silt sub-grade. The Geotechnical Investigation Report recommends bored piles for the foundations.
The basement of this building will be subjected to ground water ingress so I wish to tank the external walls and floor structure below grade. My main concerns are as follows:
If I design the basement floor slab as an overall pile cap for the concrete bored piles, how can I effectively tank the underside of the basement slab where it adjoins the bored piles?
Should I design independent pile caps for the pile groups and pour an independent floor slab over the top. This method would allow me to fully tank the underside of the basement slab.
In the above approaches I am assuming that the basement slab acts as a raft foundation for the reinforced concrete support columns of the building.
I would appreciate your feedback.
Regards
Mike
The basement of this building will be subjected to ground water ingress so I wish to tank the external walls and floor structure below grade. My main concerns are as follows:
If I design the basement floor slab as an overall pile cap for the concrete bored piles, how can I effectively tank the underside of the basement slab where it adjoins the bored piles?
Should I design independent pile caps for the pile groups and pour an independent floor slab over the top. This method would allow me to fully tank the underside of the basement slab.
In the above approaches I am assuming that the basement slab acts as a raft foundation for the reinforced concrete support columns of the building.
I would appreciate your feedback.
Regards
Mike