alanmitchell
Electrical
- Mar 22, 2004
- 9
We have a switchboard with 2 feeders and a bus tie and and two basler 3 phase diff.relays protecting the switchboard.Every motor feeder has also a ct installed and all are daisy chained together.When starting a 500kw motor on 1 feeder and a bus tie closed the diff relay used trips on all phases.The relay only has a 2 cycle delay which I think is not long enough.Has anyone worked on this relay,and can help and has anyone a CT connection for this type of scheme.Thanks in advance