BAGW
Structural
- Jul 15, 2015
- 392
Hi,
I am looking at a cantilever stub as shown below. I have always used the distance to center line of the column for the design forces (100 x 4 = 400k-ft). Seems like its very conservative approach. Can someone clarify below queries
1) Stub deign forces = 100 x 2 = 200k-ft
2) Stud weld connection to column = 100 x 2 = 200k-ft
3) Column design forces = 100 x 4 = 400k-ft
4) Column web/flange local check forces = 100 x 2 = 200k-ft or should this be 400k-ft as well?
Thanks
I am looking at a cantilever stub as shown below. I have always used the distance to center line of the column for the design forces (100 x 4 = 400k-ft). Seems like its very conservative approach. Can someone clarify below queries

1) Stub deign forces = 100 x 2 = 200k-ft
2) Stud weld connection to column = 100 x 2 = 200k-ft
3) Column design forces = 100 x 4 = 400k-ft
4) Column web/flange local check forces = 100 x 2 = 200k-ft or should this be 400k-ft as well?
Thanks