Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Beam to Pile Connection Without a Notch

jerseyshore

Structural
May 14, 2015
850
Working on a new shore house that has the same round 10" butt timber piles supporting both the first & second floors.

The original layout included having the top of the piles with a typical notch at the 2nd floor for a PSL girder.

But at the first floor, since the piles have to run up to the 2nd floor, the arch wanted to do a double beam setup (one beam on each side of the piles) without a notch to allow the piles to pass thru.

I hate these types of connections, especially on piles that dry out leaving you with loose bolts. With the reactions I calc'd so far it would require 4 bolts per beam which is unrealistic unless you have a >14" deep PSL beam on each side. I only need 3.5"x9.25" PT PSL's. And I also don't want to notch a pile midway up.

Does anyone have some good ideas for attaching that lower level of beams? It doesn't have to be a double beam setup, can just be one sided. And needs to be flood resistant construction.

I have no problem telling the arch that even though they have done this a thousand times it doesn't actually work, but it's a new client so I want to give a cost effective solution. We have this condition on almost 40 piles. Thanks all.
 
Replies continue below

Recommended for you

thick, galvanized angle as a bearing seat could work. then a bolt or two to restrain rotation of the girder.
 
Is it hard to get straight members at this height?
 
Is it hard to get straight members at this height?
No it has nothing to do with height since it's a regular 8 ft ceiling.

This particular township requires the primary living level, which in this case is not the slightly-elevated first floor (mostly gym & hangout space there), but rather the 2nd floor, to be pile supported with beams parallel to the ocean. It's the only town in NJ that I know of that has this requirement. Who doesn't love LBI.
 
thick, galvanized angle as a bearing seat could work. then a bolt or two to restrain rotation of the girder.
This is my default detail for mis-aligned piles & beam bearing repairs, so it was my first thought here as well.
 
Timber corbel. Same idea as angle except wood.
I do like this idea. Definitely less expensive than steel. Any thoughts on material? Maybe 4x6 PSL post that way we can add as many thru bolts as needed.
 
I do like this idea. Definitely less expensive than steel. Any thoughts on material? Maybe 4x6 PSL post that way we can add as many thru bolts as needed.
I don't. Has the same shrink/swell issues as bolting through the beam. It'll give you more room to put bolts in, sure, but you still have resiliency issues. And PSLs are pricey. I bet the steel is probably half the cost per foot. At the quantities you're talking about, material cost will probably be pretty close if not a little in steel's favor, and the end product will be better.
 
I don't. Has the same shrink/swell issues as bolting through the beam. It'll give you more room to put bolts in, sure, but you still have resiliency issues. And PSLs are pricey. I bet the steel is probably half the cost per foot. At the quantities you're talking about, material cost will probably be pretty close if not a little in steel's favor, and the end product will be better.

The end product is certainly a lot better with steel. And more capacity on the bolts (which also get to be a lot shorter).

If the feeling of galv angles vs PT PSL's is similar-enough cost then I'll go with steel for sure. This house is probably a $4M-5M build so I'm certainly not cheaping out on what's holding up the first floor.
 
I build a pole barn with a cont. steel beam for the joist support. I cut back the beam flange at each column and just bolted the web to the timber. Worked out nicely.
 

Part and Inventory Search

Sponsor