dean427
Chemical
- Dec 5, 2010
- 24
Hello
I apologise in advance for any ignorance here as I am not a mechanical engineer.
I am wondering if there are any industry standards or recognised best practice documents available for flange break management? I will try and articulate the specifics of what I am looking for below...
We had a safety incident on our facility during nitrogen reinstatement testing of a unit. The unit to be tested was isolated from the downstream plant by the use of actuated ball valves. Unfortunately, the ball valves were passing and this allowed nitrogen to flow into the downstream unit which contained a joint which was only finger/hand tight. The joint then failed releasing high pressure nitrogen close to where a team of operators were working.
In my view - all joints which are assembled should be tightened/torqued straight away to prevent the possibility that someone may make the system live and the joint could fail - this is how the infamous Piper Alpha incident started. In our circumstances we did not bring the downstream system under pressure intentionally but the risk of the isolation valves passing was not recognised which led to this incident.
However, I am keen to understand if it is industry best practice to mandate that all joints are immediately torqued after assembly to minimise this risk - it seems like common sense to me following Piper Alpha, but our company procedures do not seem to cover this issue.
Any help or advice is greatly appreciated!
I apologise in advance for any ignorance here as I am not a mechanical engineer.
I am wondering if there are any industry standards or recognised best practice documents available for flange break management? I will try and articulate the specifics of what I am looking for below...
We had a safety incident on our facility during nitrogen reinstatement testing of a unit. The unit to be tested was isolated from the downstream plant by the use of actuated ball valves. Unfortunately, the ball valves were passing and this allowed nitrogen to flow into the downstream unit which contained a joint which was only finger/hand tight. The joint then failed releasing high pressure nitrogen close to where a team of operators were working.
In my view - all joints which are assembled should be tightened/torqued straight away to prevent the possibility that someone may make the system live and the joint could fail - this is how the infamous Piper Alpha incident started. In our circumstances we did not bring the downstream system under pressure intentionally but the risk of the isolation valves passing was not recognised which led to this incident.
However, I am keen to understand if it is industry best practice to mandate that all joints are immediately torqued after assembly to minimise this risk - it seems like common sense to me following Piper Alpha, but our company procedures do not seem to cover this issue.
Any help or advice is greatly appreciated!