wayuu1981
Mechanical
- Sep 15, 2006
- 47
Hello,
We are about to change the reheater tubes in two 150 MW coal fired utilities, we will change 75 panels in unit 1 (100% of primary reheater) and 96 panels in unit 2 (100% of primary and secondary reheaters).
I need to know what kind of blowing-out procedure do we need to perform in order to guarantee the right steam conditions at turbine inlet prior to operation. It is necessary to perform the same blowing-out procedure we used during plant erection ? (I mean, removing reheater steam valves at turbine inlet and install a temporary piping to atmosphere, and blow the same flow of steam as we have with the unit at maximum continuous rate), or, can we perform something simpler, considering we will only change reheater tubes, but we have the same water walls, steam drum, steam lines, SH and RH headers, etc.?
I’m asking this because the contractor that will change the reheater tubes will propose a blowing-out procedure and I need to establish the minimum requirements they have to include in their blowing-out scope.
I will appreciate your help
Javier Guevara E.
Projects Engineer
Javier Guevara E.
Projects, Mechanical Engineer
TERMOGUAJIRA - GECELCA S.A. E.S.P.
We are about to change the reheater tubes in two 150 MW coal fired utilities, we will change 75 panels in unit 1 (100% of primary reheater) and 96 panels in unit 2 (100% of primary and secondary reheaters).
I need to know what kind of blowing-out procedure do we need to perform in order to guarantee the right steam conditions at turbine inlet prior to operation. It is necessary to perform the same blowing-out procedure we used during plant erection ? (I mean, removing reheater steam valves at turbine inlet and install a temporary piping to atmosphere, and blow the same flow of steam as we have with the unit at maximum continuous rate), or, can we perform something simpler, considering we will only change reheater tubes, but we have the same water walls, steam drum, steam lines, SH and RH headers, etc.?
I’m asking this because the contractor that will change the reheater tubes will propose a blowing-out procedure and I need to establish the minimum requirements they have to include in their blowing-out scope.
I will appreciate your help
Javier Guevara E.
Projects Engineer
Javier Guevara E.
Projects, Mechanical Engineer
TERMOGUAJIRA - GECELCA S.A. E.S.P.