Hello All,
As a regular visitor to the forum, I wanted to thank everyone for all of the valuable information available for reference. I have found myself frequenting the site in the past few months, but have not needed to propose my own question until now:
A customer recently inquired about having an old steam tube boiler converted into a hot water storage tank. Apparently the vessel is located on the top floor of a local hotel and is soon to replaced with smaller, more efficient boilers. However, given the location of the vessel and lack of roof-top cranes, it is likely impossible to remove the boiler from the building. Instead, the customer would like to know if it is possible to convert the boiler into a hot water storage tank (i.e. removing all tubes and tubesheets, weld new solid tubesheets in place of originals, weld 'doors' shut, etc... as necessary for safely sustaining pressure of water storage tank)
My company is an ASME certified repair facility, holding ASME, U, and R stamps. I am aware that re-purposing the vessel will likely fall outside of the scope of a typical "alteration" as per NBIC, but just curious if anyone out there has any experience or expertise regarding the situation at hand. Any and all information would be greatly appreciated, thanks in advance!
As a regular visitor to the forum, I wanted to thank everyone for all of the valuable information available for reference. I have found myself frequenting the site in the past few months, but have not needed to propose my own question until now:
A customer recently inquired about having an old steam tube boiler converted into a hot water storage tank. Apparently the vessel is located on the top floor of a local hotel and is soon to replaced with smaller, more efficient boilers. However, given the location of the vessel and lack of roof-top cranes, it is likely impossible to remove the boiler from the building. Instead, the customer would like to know if it is possible to convert the boiler into a hot water storage tank (i.e. removing all tubes and tubesheets, weld new solid tubesheets in place of originals, weld 'doors' shut, etc... as necessary for safely sustaining pressure of water storage tank)
My company is an ASME certified repair facility, holding ASME, U, and R stamps. I am aware that re-purposing the vessel will likely fall outside of the scope of a typical "alteration" as per NBIC, but just curious if anyone out there has any experience or expertise regarding the situation at hand. Any and all information would be greatly appreciated, thanks in advance!